Trenchless directional drilling construction process-4
Equipment dismantled, landform restoration
(1) After completing the crossing, clean and adjust the equipment, and evacuate the construction site.
(2) Treatment of backflow mud: The mud in the mud pool on the side of the earth and the excavation shall be treated after consultation with Party A. It is recommended to bury it on the spot or transport it to a treatment plant designated by the local environmental protection department for treatment, and then perform landform restoration.